Beyon Announces Third Data Center to Run Entirely on Renewable Energy
Beyon plans to bring its renewable-powered data center portfolio to three facilities through Phase 5 of its Solar Park program. The company announced the expansion at Gateway Gulf 2026, attended by Beyon Group Chairman Shaikh Abdulla bin Khalifa Al Kha...

Key points
- Phase 5 was carried out with Almoayyed Solar at a cost of approximately BD544,500, according to Bahrain News Agency.
- The 14,000-square-meter site houses 2,292 solar panels providing 1.5 MWp of capacity.
- Annual generation from Phase 5 is projected at about 2.5 GWh of clean electricity, cutting emissions by over 1,585 metric tons a year.
- Phase 4 brought renewable power to Total CX's Customer Contact Centre, described as Bahrain's first such facility using renewable energy.
- Phase 3 at Hamala lets Beyon's Tier III data center run entirely on renewable energy, with solar serving as a redundant power source.
Phase 5 investment and expected output
Bahrain News Agency reported that Beyon carried out Phase 5 with Almoayyed Solar at a cost of approximately BD544,500. Across a 14,000-square-meter site, 2,292 solar panels provide 1.5 MWp of capacity.
The announcement described Phase 5 as completed, while placing completion and its expected output in the coming months. Annual generation is projected at about 2.5 GWh of clean electricity, with carbon dioxide emissions reduced by more than 1,585 metric tons a year.
Beyon is expanding its renewable energy infrastructure as demand for data, cloud and digital services grows. Group CEO Andrew Kvaalseth said data centers are essential to the digital economy and that their growth must account for sustainability. He called reaching three green data centers a major milestone in the company's renewable energy program.
Earlier projects and power resilience
The Solar Park also supplies facilities beyond Beyon's data centers. Phase 4, completed in 2026, brought renewable power to Total CX's Customer Contact Centre, described by Bahrain News Agency as Bahrain's first such facility to use renewable energy.
At Hamala, Phase 3 enabled Beyon's Tier III-certified data center to operate entirely on renewable energy. Completed in 2025 and announced at that year's Gateway Gulf event, the project cost BHD520,000, or about US$1.4 million. Its 2,588 high-efficiency panels occupy more than 13,000 square meters.
Developing Telecoms reports that Phase 3 produces approximately 2.5 GWh of clean electricity annually and cuts carbon dioxide emissions by 1,777 metric tons a year. Beyon says the solar infrastructure also provides another source of redundant power alongside generators and Electricity and Water Authority (EWA) feeds, helping maintain continuous operation of mission-critical systems.
The Hamala data center opened in 2021 with 2.75 MW of capacity and room for 250 racks, according to Data Centre Dynamics. Beyon also operates a colocation facility in Manama.
Renewable energy across Beyon's infrastructure
In its current sustainability disclosures, Beyon says its Tier III data centers at Beyon Data Oasis and Hamala operate entirely on renewable energy. The company describes them as Bahrain's first net-zero Tier III data centers. Including other renewable energy investments across the business, the Green Energy Programme generates more than 6.7 GWh of clean electricity and avoids more than 4,711 metric tons of carbon dioxide emissions annually, Beyon says.
Mohammed Almoayyed, chairman of Almoayyed International Group, said the work with Beyon demonstrated how partnerships can deliver large-scale renewable energy infrastructure. The collaboration with Almoayyed Solar is a long-term effort to extend renewable power across Beyon's infrastructure and support Bahrain's sustainability and carbon-reduction goals.